Monthly Status Report For Re-construction of Govt. Primary School
under Reconstruction & Renovation Project(2nd. & 3rd Phase)FY-2011-2012
Division: Rajshahi, District: Pabna Reporting Month/Date: June’2012
NAME OF GOVT. PRY. SCHOOL | TYPE OF WORK | ESTIMATED COST | ENLISTED YEAR | CONTRACT AMOUNT | NAME OF CONTRACTOR | DATE OF CONTRACT | DATE OF COMPLE- TION | PRECEN- TAGE ACCOM-PLISHED | AMOPUNT SPENT | REMARKS |
1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 | 9 | 10 | 11 |
UPAZILA: CHATMOHAR | ||||||||||
Jaborkol GPS Package No.GPSRRP/WD5.402 | Reconstruction & Renovation | 37,10,000.00 Revised Tk. 36,70,000/= | 2011-2012 | 35,24,500.00 Revised Tk. 34,86,500/= | M/S. Sumon Enterprise Goespur, Pabna | 13-11-2011 | 30-06-2012 | 30% | - |
|
Jogtola GPS Package No.GPSRRP/WD9.490 | Reconstruction & Renovation | 37,10,000.00 Revised Tk. 26,33,500.00 | 2011-2012 | 25,01,825.00 | M/S. Abul Bashar, Pop. Mirza Abul Bashar, Pailanpur, Pabna. | 11-01-2012 | 10-06-2012 | 70% | - |
|
Handial GPS Package No.GPSRRP/WD5.764 | Reconstruction & Renovation | 37,10,000.00 Revised Tk. 36,70,000/= | 2011-2012 | 35,24,500.00 Revised Tk. 34,86,500/= | M/S. Sheikh Enterprise Prop. Md. Yousuf Ali Sheikh Grurudaspur, Pabna. | 11-01-2012 | 20-06-2012 | 40% | - |
|
Total Tk.
|
|
|
| - |
|
|
|
| - |
|
Accountant Sub-Asst. Engineer, Upazila Engineer
LGED., Chatmohar, Pabna. LGED., Chatmohar, Pabna. LGED., Chatmohar, Pabna.
Progress Report-A4/1
Monthly Status Report For Need Based Basis Repair/Renovation work of
Government Primary SchoolFY-2011-2012
Division: Rajshahi,
Upazila: Chatmohar, District: Pabna Reporting Month/Date: June’2012
NAME OF GOVT. PRY. SCHOOL | TYPE OF WORK | ESTIMATED COST | ENLISTED YEAR | CONTRACT AMOUNT | NAME OF CONTRACTOR | DATE OF CONTRACT | DATE OF COMPLE- TION | PRECEN- TAGE ACCOM-PLISHED | AMOPUNT SPENT | REMARKS |
1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 | 9 | 10 | 11 |
01. Handial Govt. Primary school
| Repair | 292,500/= | 2011-2012 | 277,875.00 | Md. Ashraful Alam Krishnopur, Pabna. | 11-01-2012 | 31-01-2012 | 100% | 277,875.00 |
|
02. Shalikha Govt. Primary school | Repair | 297,090/= | 2011-2012 | 282,235.00
| M/S. Moushuni Enterpirse Prop. Md. Montaj Ali Alaipur, Natore | 15-01-2012 | 31-01-2012 | 100% | 282,235.00
|
|
03. Amritakunda Govt. Primary school | Repair | 258,600/= | 2011-2012 | 245,670.00 | M/S. Akash Traders Prop. Ananda Kumar shaha Chatmohar, Pabna. | 11-01-2012 | 31.01-2012 | 100% | 245,670.00 |
|
Accountant Sub-Asst. Engineer, Upazila Engineer
LGED., Chatmohar, Pabna. LGED., Chatmohar, Pabna. LGED., Chatmohar, Pabna.
Progress Report-A4/2
May’2012 Page No. 1 of1
MONTHLY STATUS REPORT FOR REGISTERED NON-GOVT. PRIMARY SCHOOL DEVELOPMENT PROJECT(3RD. PHASE)
EXTENSION OF REGISTERED NON-GOVT. PRIMARY SCHOOL WITH ELECTRIFICATION & FURNITURE SUPPLY:FY-2011-2012
NAME OF REGD. NON-GOVT. PRY. SCHOOL | ESTIMATED COST | TYPE OF EXTENSION | ENLISTED YEAR | CONTRACT AMOUNT | NAME OF CONTRACTOR | DATE OF CONTRACT | DATE OF COM-PLETEION | PERCENTAGE ACCOM-PLISHED | AMOUNT SPENT | REMARKS |
Chhaikola Sabujpara RNGPS Package No. RNGPS/WD4.2015
| 28,90,000.00 Revised: 33,22,000/= | Horizontal Extension | 2011-2012 | 27,45,500.00 Revised: 31,55,900/= | M/S. Bhulu Sarker Alaipur, Natore | 02-02-12 | 30-09-12 | 25% |
|
|
Debipur RNGPS Package No. RNGPS/WD4.2016
| 28,90,000.00 Revised: 33,22,000/= | Horizontal Extension | 2011-2012 | 27,45,500.00 Revised: 31,55,900/= | M/S. Rubel Enterprise Chatmohar, Pabna | 01-02-12 | 30-09-12 | 40% |
|
|
Shontospur RNGPS Package No. RNGPS/WD4.2017
| 28,90,000.00 Revised: 33,22,000/= | Horizontal Extension | 2011-2012 | 27,45,500.00 Revised: 31,55,900/= | M/S. Rani Enterprise Bhangoora, Pabna. | 08-02-12 | 30-09-12 | 10% |
|
|
Khatabari Puranpara RNGPS Package No. RNGPS/WD4.2018
| 28,90,000.00 Revised: 33,22,000/= | Horizontal Extension | 2011-2012 | 27,45,500.00 | M/S. Azam Builders Paschim Shadhupara, Pabna | 13-02-12 | 30-09-12 |
|
| RvqMv mgm¨v| mv‡f© Kivi mgq ¯‹zj KZ©„c¶ †h RvqMv †`Lvb †j-AvDU cÖ`vbKv‡j †`Lv hvq D³ RvqMv e¨w³ gvwjKvbvaxb nIqvq KvRwU evwZ‡ji Rb¨ mycvwik Kviv n‡q‡Q| |
Total | 115,60,000.00
|
|
| 109,82,000.00
|
|
|
|
|
|
|
Accountant Sub-Asst. Engineer, Upazila Engineer
LGED., Chatmohar, Pabna. LGED., Chatmohar, Pabna. LGED., Chatmohar, Pabna.
Progress Report/3
Progress Report for Project Period
Project Name: Construction of Union Parishad Complex Bhaban : FY- 2009-2010, 2010-2011
District: Pabna. Reporting Month/Date: June’2012
Sl. No.
| Upazila Name | Code/ ID No. | Name of Scheme | Length/ Quantity (Km/m/ No.) | Allocation (Tk.) | Date of Alloca-tion | Estimated Cost (Tk.) | Date of Approval | Name of Contractor | Contract Amount (Tk.) | Date of Work Order | Date of Completion | Physical Pro-gress | Payment made (Tk.) | Remarks |
1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 | 9 | 10 | 11 | 12 | 13 | 14 | 15 | 16 |
01 | Chatmohar |
| 2009-2010 Contruction of Beel Chalan Union Parishad Complex Bhaban |
01(one) |
59,00,000.00 |
13-12-09 |
59,00,000.00 |
05-04-10 | Confidence Associate |
56,05,000.00 |
13-04-10 |
11-10-10 |
95% | 50,00,000/= |
|
02 | -do- |
| 2009-2010 Contruction of Mathurapur Union Parishad Complex Bhaban |
01(one) |
59,00,000.00 |
12-04-10 |
59,00,000.00 |
05-07-10 | Habib Enterprise, Sujanagar, Pabna |
56,05,000.00 |
26-07-10 |
21-01-2011 |
70% | 25,00,000/= |
|
03 | -do- |
| 2009-2010 Contruction of Handial Union Parishad Complex Bhaban |
01(one) |
59,00,000.00 |
13-05-10 |
59,00,000.00 |
24-10-10 | Md. Shahidul Alam, Bhangoora, Pabna. |
56,05,000.00 | 21-11-10 | 20-05-11 | 90% | 20,00,000/= |
|
04 | -do- |
| 2009-2010 Contruction of Parshaw-danga Union Parishad Complex Bhaban |
01(one) |
59,00,000.00 |
13-05-10 |
59,00,000.00 |
24-10-10 | Md. Molsur Ali sheikh Montu Sujanagar, Pabna |
56,05,000.00 | 21-11-10 | 20-05-11 | 60% | 5,00,000/= |
|
05 | -do- |
| 2009-2010 Contruction of D.B.gram Union Parishad Complex Bhaban | 01(one) |
59,00,000.00 |
13-05-10 |
59,00,000.00 |
24-10-10 | Saiful Islam, Atua, Pabna |
56,05,000.00 | 21-11-10 | 20-05-11 | 90% | 20,00,000/= |
|
06 | -do- |
| 2009-2010 Contruction of Chhaikola Union Parishad Complex Bhaban | 01(one) |
59,00,000.00 |
13-05-10 |
59,00,000.00 |
24-10-10 | Habib Enterprise, Sujanagar, Pabna |
56,05,000.00 | 28-11-10 | 20-05-11 | 40% | 15,00,000/= |
|
Accountant Sub-Asst. Engineer Upazila Engineer
LGED., Chatmohar, Pabna. LGED., Chatmohar, Pabna. LGED., Chatmohar, Pabna.
Progress Report-A4/4
Progress Report for Regional Server Station
Project Name: Construction of Upazila & Regional Server Station for Electrolal Database : FY- 2010-2011
District: Pabna. For theMonth of : June’2012
Sl. No. | Name of Upazila | Name of the Project | Allocation Tk. | Estimated Cost Tk. | Name of the Contractor | Contract Amount Tk. | Date of Work Order | Date of Completion as per Work Order | Progress (%) | Fund Release | Fund Spent | Remarks |
1 | 2 | 2 | 3 | 4 | 5 | 6 | 7 | 8 | 9 | 10 | 11 | 12 |
01 | Chatmohar | Construction of Upazila & Regional Server Station for Electrolal Database in Bhangoora, Faridpur & Chatmohar Upazila, District-Pabna. (Contract Package No.PBN/2)
| 82,95,000/= | 82,95,000/= | M/S. Unique Traders Prop. Md. Anowar Hossain Gobindagunia, Mirpur, Kushtia |
69,84,952.00 |
26-09-2010 |
26-04-2011 |
100% |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Accountant Sub-Asst. Engineer Upazila Engineer
LGED., Chatmohar, Pabna. LGED., Chatmohar, Pabna. LGED., Chatmohar, Pabna.
Progress Report-A4/5
¯’vbxq miKvi cÖ‡KŠkj Awa`ßi
cÖK‡íi bvg t- 2010-2011 A_© eQ‡i AMÖwaKvi wfwˇZ ¸i“Z¡c~Y© cjx AeKvVv‡gv Dbœqb kxl©K cÖKí (IRIDP)-Gi AvIZvq ev¯—evqbvaxb Kv‡Ri gvwmK AMÖMwZi cÖwZ‡e`b
Dc‡Rjv t PvU‡gvni, †Rjvt cvebv| cÖwZ‡e`‡bi gvm/ZvwiLt RybÕ2012
µwgK bs | cÖK‡íi bvg | ‡gvU eivÏ | cÖv°wjZ g~j¨ | Pyw³g~j¨ ( UvKv) | wVKv`v‡ii bvg I wVKvbv | Kvh©v‡`‡ki ZvwiL | Kvh©v‡`k †gvZv‡eK KvR mgvwßi ZvwiL | Kv‡Ri AMÖMwZ | cÖvß A_© | ‡gvU e¨q | gš—e¨ |
1 | 2 | 3 | 4 | 5 | 6 | 87 | 8 | 9 | 10 | 11 | 12 |
01 | AMÖwaKvi wfwˇZ ¸i“Z¡c~Y© cjx AeKvVv‡gv Dbœqb kxl©K cÖK‡íi AvIZvq PvU‡gvni †ijevRvi-RMZjv c~e©cvov †ij‡MU (gnigLvwj †ij‡MU) fvqv RMZjv gv`ªvmv iv¯—v (†PB‡bR 3200-4700wgt) Dbœqb (c¨v‡KR bs-IRIDP/PBN/W-17)| | 23,94,934/= | 23,94,934/= | 22,75,187/= | ‡gmvm© ˆkke cÖWvKkb †m›Uvi‡cÖvt- †gvt myjZvb gvngy` KvPvixcvov, cvebv | 20-09-10 | 14-06-11 | 100% |
|
|
|
02 | AMÖwaKvi wfwˇZ ¸i“Z¡c~Y© cjx AeKvVv‡gv Dbœqb kxl©K cÖK‡íi AvIZvq Ag„ZKzÛv wRwm-wWweMÖvg BDwc Awdm iv¯—v(†PB‡bR 3000-4500wgt) Dbœqb (c¨v‡KR bs-IRIDP/PBN/W-16 | 53,82,512/= | 53,82,512/= | 51,13,386/= | Rbve †gvt wgRvbyi ingvb,‡cÖvt- †gvt wgRvbyi ingvb,mvs-ebcvov nv‡ivqv, Dc‡Rjv-eovBMÖvg, †Rjv-bv‡Uvi | 13-10-10 | 15-07-11 | 100% |
|
|
|
03 | AMÖwaKvi wfwˇZ ¸i“Z¡c~Y© cjx AeKvVv‡gv Dbœqb kxl©K cÖK‡íi AvIZvq ‡bDwZMvQv Avi GÛ GBP-kirMÄ wRwm fvqv ˆdjRvbv nvU iv¯—v Dbœqbb(c¨v‡KR bs-IRIDP/PBN/W-41) | 69,10,294/= | 69,10,294/= | 65,64,779/= | ‡gmvm© miKvi Kb÷ªvKkb, ‡cÖvt- †gvt Avt QvËvi miKvi,‡mvbvnviv,Dc‡Rjv- dwi`cyi, †Rjv-cvebv| | 27-09-10 | 31/07/10 | 100% |
|
|
|
04 | AMÖwaKvi wfwˇZ ¸i“Z¡c~Y© cjx AeKvVv‡gv Dbœqb kxl©K cÖK‡íi AvIZvq ‰djRvbv g`b kvn evox-mvBcvuB †LRyi evMvb iv¯—v (†PB‡bR 00-1000wgt) Dbœqb (c¨v‡KR bs-DP/PBN/ W-13)| | 29,93,667/= | 29,93,667./= | 28,43,984/= | ‡gmvm© mi`vi GÛ mÝ ‡cÖvt- Gm Gg gwZDi ingvb,Ck¦i`xv, cvebv | 12-10-10 | 16-07-11 | 100% |
|
|
|
05 | AMÖwaKvi wfwˇZ ¸i“Z¡c~Y© cjx AeKvVv‡gv Dbœqb kxl©K cÖK‡íi AvIZvq ¸bvBMvQv nvU Avi GÛ GBP Picvov Avi GÛ GBP fvqv ˆcjvbcyi iv¯—v (†PB‡bR 00-800wgt) Dbœqb (c¨v‡KR bs-IRIDP/ PBN/ W-14 | 27,84,177/= | 27,84,177/= | 26,44,968/= | †gmvm© Bmjvg G›UvicÖvBR ‡cÖvt- Gm,Gg bRi“j Bmjvg. PvU‡gvni, cvebv| | 05-10-10 | 23-06-11 | 100% |
|
|
|
wnmve i¶K DcmnKvix cÖ‡KŠkjx Dc‡Rjv cÖ‡KŠkjx
Dc‡Rjv cÖ‡KŠkjxi `ßi Dc‡Rjv cÖ‡KŠkjxi `ßi PvU‡gvni, cvebv|
PvU‡gvni, cvebv| PvU‡gvni, cvebv|
¯’vbxq miKvi cÖ‡KŠkj Awa`ßi
cÖK‡íi bvg t- 2010-2011 A_© eQ‡i AMÖwaKvi wfwˇZ ¸i“Z¡c~Y© cjx AeKvVv‡gv Dbœqb kxl©K cÖKí (IRIDP)-Gi AvIZvq ev¯—evqbvaxb Kv‡Ri gvwmK AMÖMwZi cÖwZ‡e`b
Dc‡Rjv t PvU‡gvni, †Rjvt cvebv| cÖwZ‡e`‡bi gvm/ZvwiLt RybÕ2012
µwgK bs | cÖK‡íi bvg | ‡gvU eivÏ | cÖv°wjZ g~j¨ | Pyw³g~j¨ ( UvKv) | wVKv`v‡ii bvg I wVKvbv | Kvh©v‡`‡ki ZvwiL | KvR mgvwßi ZvwiL | Kv‡Ri AMÖMwZ | cÖvß A_© | ‡gvU e¨q | gš—e¨ |
1 | 2 | 3 | 4 | 5 | 6 | 87 | 8 | 9 | 10 |
| 12 |
06 | AMÖwaKvi wfwˇZ ¸i“Z¡c~Y© cjx AeKvVv‡gv Dbœqb kxl©K cÖK‡íi AvIZvq PvU‡gvni Dc‡Rjvaxb PoB‡Kvj †Kqvi iv¯—v-PoB ‡Kvj nvU fvqv gv`ªvmv iv¯—v (†PB‡bR 00-1000wgt ) Dbœqb (c¨v‡KR bs-IRIDP/PBN/W-15) | 29,93,667/= | 29,93,667/= | 28,43,984/= | Rbve kªx `yjvj Kg©Kvi, PvU‡gvni cyivZb evRvi, PvU‡gvni, cvebv| | 19-11-10 | 23-07-11 | 100% |
|
|
|
07 | AMÖwaKvi wfwˇZ ¸i“Z¡c~Y© cjx AeKvVv‡gv Dbœqb kxl©K cÖK‡íi AvIZvq PvU‡gvni Dc‡Rjvaxb Kv‡qg‡Kvjv Avi GÛ GBP †gvo-wc‡ob evRvi fvqv fevbxcyi †fjvevwoqv iv¯Ív (‡PB‡bR 00-1000wgt ) Dbœqb (c¨v‡KR bs-IRIDP/ PBN/W-75) | 32,81,581/= | 32,81,581/= | 36,04,747/= | †gvt kvnRvnvb Avjx, wUwe †ivW, j¶xcyi, ivRkvnx| | 18-08-11 | 31-01-12 | 40% |
|
|
|
08 | AMÖvwaKvi wfwˇZ ¸i“Z¡c~Y© cjx AeKvVv‡gv DbœqbÓ kxl©K cÖK‡íi AvIZvq PvU‡gvni Dc‡Rjvaxb cvuPzwiqv cvKv iv¯Ív evH‡Kvjv Avi GÛ GBP fvqv w`jvjcyi mit cÖv_t we`¨vjq iv¯Ív (‡PB‡bR 00-2000wgt) Dbœqb(c¨v‡KR bs-IRIDP/PBN/W-76) | 67,26,263/= | 67,26,263/= | 73,58,400/= | †gvt kvnRvnvb Avjx, wUwe †ivW, j¶xcyi, ivRkvnx| | 18-08-11 | 31-01-12 | 80% |
|
|
|
9 | ÒAMÖvwaKvi wfwˇZ ¸i“Z¡c~Y© cjx AeKvVv‡gv DbœqbÓ kxl©K cÖK‡íi AvIZvq PvU‡gvni Dc‡Rjvaxb PoB‡Kvj †Kqvi iv¯Ív-PoB‡Kvj nvU fvqv PoB‡Kvj gv`ªvmv iv¯Ív Dbœqb(†PB‡bR 800-1620wgt) (c¨v‡KR bs-IRIDP/ PBN/W-77) | 27,65,778/= | 27,65,778/= | 30,10,621/= | †gvt wRbœvZ Avjx wRbœvn cvUwKqvcvov, cvebv| | 24-0811 | 18-02-12 | 70% |
|
|
|
10 | MÖvwaKvi wfwˇZ ¸i“Z¡c~Y© cjx AeKvVv‡gv Dbœqb kxl©K cÖK‡íi AvIZvq PvU‡gvni Dc‡Rjvaxb fv`ªv AviGBPwW(g_yivcyi BDwc)-PoB‡Kvj fvqv g_yivcyi ¯yBP †PM moK(†PB‡bR 6000-8000wgt) Dbœqb (c¨v‡KR bs-IRIDP/PBN/W-105) | 82,67,000/= | 82,67,000/= | 78,53,650/= | =†gvt †mwjg †nv‡mb ‡Mvcvjcyi, cvebv| | 22-03-12 | 28-09-12 | 0% |
|
|
|
11 | AMÖwaKvi wfwˇZ ¸i“Z¡c~Y© cjx AeKvVv‡gv Dbœqb kxl©K cÖK‡íi AvIZvq (K) nwicyi BDwc-†Mvcvjcyi †dixNvU moK (‡PB‡bR 00-1000wgt) Dbœqb Ges (L) D³ iv¯Ívi 17wgt I 171wgt †PB‡b‡R `yBwU BD-†Wªb wbg©vY(c¨v‡KR bs-IRIDP/ PBN/W-106)| | 43,28,000/= | 43,28,000/= | 41,11,600/= | ‡gmvm© bvBP †UªWvm~ myRvbMi, cvebv| | 14-03-12 | 21-09-12 | 60% |
|
|
|
wnmve i¶K DcmnKvix cÖ‡KŠkjx Dc‡Rjv cÖ‡KŠkjx
Dc‡Rjv cÖ‡KŠkjxi `ßi Dc‡Rjv cÖ‡KŠkjxi `ßi PvU‡gvni, cvebv|
PvU‡gvni, cvebv| PvU‡gvni, cvebv|
AMÖMwZ cÖwZ‡e`b/7
¯’vbxq miKvi cÖ‡KŠkj Awa`ßi
2008-09 A_© eQ‡i BDwbqb moK I Ab¨vb¨ AeKvVv‡gv Dbœqb cÖKí(e„nËi e¸ov, ivRkvnx I cvebv †Rjv)kxl©K cÖK‡íi
gvwmK AMÖMwZi cÖwZ‡e`b
Dc‡Rjv t PvU‡gvni, †Rjvt cvebv| cÖwZ‡e`‡bi gvm/ZvwiLt RybÕ2012
µwgK bs | cÖK‡íi bvg | ‡gvU eivÏ | cÖv°wjZ g~j¨ | wVKv`v‡ii bvg I wVKvbv | Pzw³g~j¨ (UvKv) | Kvh©v‡`‡ki ZvwiL | Kvh©v‡`k †gvZv‡eK KvR mgvwßi ZvwiL | Kv‡Ri AMÖMwZ | cÖvß A_© | ‡gvU e¨q | gš—e¨ |
1 | 2 | 3 | 4 | 5 | 6 | 87 | 8 | 9 | 10 | 11 | 12 |
01 | 2009-2010 A_© eQ‡i nvwÛqvj BDwc Awdm-bIMvu fvqv evNjevox ˆK iv¯—v Dbœqb(†PB‡bR 3080-4580wgt) | 45,20,142/= | 45,20,142/= | †gvt kvnRvnvb Avjx, wUwe †ivW, j¶xcyi, ivRkvnx | 39,77,663/= | 18-11-09 | 30-05-10 | 70% |
|
|
|
02 | 2009-2010 A_© eQ‡i PvU‡gvni wU GÛ wU †gvo-nwicyi BDwc Awdm fvqv ivgbMi, ayjvDwo, SvKov fvqv †Rvo`n iv¯—v Dbœqb(†PB‡bR 00-1250wgt) | 40,01,101/= | 40,01,101/= | †g&t AvdRvj †nv‡mb, dwi`cyi, cvebv| | 37,16,031/= | 02-12-09 | 06-04-10 | 70% |
|
| Remai-ning Estimate cvVv‡bv n‡q‡Q| |
03 | 2009-2010 A_© eQ‡i nvwÛqvj BDwc Awdm-bIMvu fvqv evNjevox ˆK iv¯—vq 3280wgt †PB‡b‡R 4.00x 3.60wgt Aviwmwm e· KvjfvU© Ges 34701wgt †PB‡b‡R BD-‡Wªb wbg©vY| | 16,67,267/= | 16,67,267/= | ‡gmv©m Qvjvg GÛ †Kvs, evwjqv nvjU, cvebv| | 12,83,075/= | 09-11-09 | 15-03-10 | 100% |
|
|
|
04 | 2009-2010 A_© eQ‡i g_yivcyi BDwc Awdm-KvUv Lvwj nvU iv¯—v Dbœqb(‡PB‡bR 3270-6344wgt)
| 75,29,577/= | 75,29,577/= | †gvt kvnRvnvb Avjx, wUwe †ivW, j¶xcyi, ivRkvnx | 65,50,687/= | 16-11-09 | 19-08-10 | 100% |
|
|
|
05 | 2009-2010 A_© eQ‡i BDwbqb moK I Ab¨vb¨ AeKvVv‡gv Dbœqb cÖKí (e„nËi e¸ov, ivRkvnx I cvebv †Rjv) Gi AvIZvq Improvement of (a) Pabakhali-Shohagbari road at Ch. 00-175m.,(b) Shohagbari pucca road-Professor Boyenuddin house road at Ch.00-150m. | 12,25,606/= | 12,25,606/= | †gmvm© cÖMwZ G›UvicÖvBR, †cÖvt- †mv‡nj nvmvb kvnxb, evwjqv nvjU, cvebv| | 11,64,325/= | 03-10-10 | 23-06-11 | 100% |
|
|
|
wnmve i¶K Dc-mnKvix cÖ‡KŠkjx Dc‡Rjv cÖ‡KŠkjx
Dc‡Rjv cÖ‡KŠkjxi `ßi Dc‡Rjv cÖ‡KŠkjxi `ßi PvU‡gvni, cvebv|
PvU‡gvni, cvebv| PvU‡gvni, cvebv|
AMÖMwZ cÖwZ‡e`b/8
¯’vbxq miKvi cÖ‡KŠkj Awa`ßi
2010-2011 A_© eQ‡i ‡`‡ki DËi-cwðgv‡ji Dc‡Rjvmg~‡ni (cvebv, wmivRMÄ, bv‡Uvi, bIMvu, ivRkvnx, beveMÄ I e¸ov †Rjv) moK, †mZz/KvjfvU©© Dbœqb cÖK‡íi AvIZvq
gvwmK AMÖMwZi cÖwZ‡e`b
Dc‡Rjv t PvU‡gvni, †Rjvt cvebv| cÖwZ‡e`‡bi gvm/ZvwiLt RybÕ2012
µwgK bs | cÖK‡íi bvg | ‡gvU eivÏ | cÖv°wjZ g~j¨ | wVKv`v‡ii bvg I wVKvbv | Pzw³g~j¨ (UvKv) | Kvh©v‡`‡ki ZvwiL | Kvh©v‡`k †gvZv‡eK KvR mgvwßi ZvwiL | Kv‡Ri AMÖMwZ | cÖvß A_© | ‡gvU e¨q | gš—e¨ |
1 | 2 | 3 | 4 | 5 | 6 | 87 | 8 | 9 | 10 | 11 | 12 |
01 | 2008-09 A_© eQ‡i evgbMÖvg nvU-`qvivgcyi iv¯—v I Kvgvjcyi iv¯—v Dbœqb(†PB‡bR 350-1580 wgt) | 52,74,584/= | 52,74,584/= | ‡gvt AvRMi Avjx, `w¶Y eoMvQv, bv‡Uvi | 50,10,854/= | 13-06-10 | 30-02-11 | 100% |
|
|
|
02 | 2009-10 A_© eQ‡i kirMÄ evRvi- RMbœv_cyi fvqv Bw`jcyi iv¯—v Dbœqb (†PB‡bR 00-3200wgt I 4200-6000 wgt) | 207,58,045/= | 207,58,045/= | gv Kb÷ªvKkb, PK QvwZqvwb, cvebv | 181,36,807/= | 25-07-10 | 06-06-11 | 70% |
|
|
|
03 | 2010-11A_© eQ‡i g_yivcyi BDwc Awdm- wWweMÖvg BDwc Awdm(evnv`yicyi-gvRMÖvg) (‡PBt 00-5000wgt moKDbœqb| | 183,43,594/= | 183,43,594/= | †gvt kvnRvnvb Avjx wUwe†ivW, j¶xcyi, ivRkvnx| | 174,26,414/= | 20-07-10 | 30-02-11 | 70% |
|
|
|
04 | 2010-11 A_© eQ‡i PvUgvni Dc‡Rjv †nW †KvqvU©vi(nvB¯‹zj †gvo-wbwkcvov)-g‡njv wRwm fvqv e„-¸qvLov (g‡njv KvwiMicvov iv¯—v-‡PBt 00-1000wgt) Dbœyqb (c¨v‡KR bs-PAB/ IRBNWRC/ W-003) | 36,11,273/= | 36,11,273/= | ‡gvt ivqnvbyj Bmjvg, ebIqvixbMi,dwi`cyi cvebv| | 34,30,709/= | 20-09-10 | 31-07-11 | 30% |
|
|
|
05 | 2010-11 A_© eQ‡i PvUgvni Dc‡Rjvq 3(wZb)wU Aviwmwm e· KvjfvU© wbg©vY(c¨v‡KR bs-PAB/-ST-VR-(24, 25 & 26)/ 10-11 |
34,84,375/= |
34,84,375/= |
†gmvm© bqb Ki‡cv‡ikb ‡cÖvt †gvt Kwigy¾vgvb, AvUzqv wWwm †ivW,cvebv| |
33,10,156/= |
27-10-10 |
31-07-11 |
|
|
|
|
(1) cvUzjx cvov-cvk¦©WvsMv- nv`j iv¯—vi kvnRvnv‡bi Rwgi Dci 2 †f‡›Ui4.00wgt x 4.00wgt Aviwmwm e· KvjfvU | 100% |
|
|
| |||||||
(2) wkqvjv-mi`vi cvov iv¯—vi 700 wgt †PB‡bR 3 †f‡›Ui 4.00 wgx 4.00wg Aviwmwm e· KvjfvU | 100% |
|
|
| |||||||
(3) evgbMÖvg †ij †MU- `qvivgcyi iv¯—vi cv‡k¦© Mdzovev` †ij †ók‡bi K¨v‡b‡ji Dci 2.00 wgt x 2.00wgt 2 †f›U Aviwmwm e· KvjfvU wbg©vY | - |
|
| evwZ‡ji Rb¨ mycvvwk Kiv n‡q‡Q |
wnmve i¶K Dc-mnKvix cÖ‡KŠkjx Dc‡Rjv cÖ‡KŠkjx
Dc‡Rjv cÖ‡KŠkjxi `ßi Dc‡Rjv cÖ‡KŠkjxi `ßi PvU‡gvni, cvebv|
PvU‡gvni, cvebv| PvU‡gvni, cvebv|
AMÖMwZ cÖwZ‡e`b/9
2q cvZv
Dc‡Rjv t PvU‡gvni, †Rjvt cvebv| cÖwZ‡e`‡bi gvm/ZvwiLt RybÕ2012
µwgK bs | cÖK‡íi bvg | ‡gvU eivÏ | cÖv°wjZ g~j¨ | wVKv`v‡ii bvg I wVKvbv | Pzw³g~j¨ (UvKv) | Kvh©v‡`‡ki ZvwiL | Kvh©v‡`k †gvZv‡eK KvR mgvwßi ZvwiL | Kv‡Ri AMÖMwZ | cÖvß A_© | ‡gvU e¨q | gš—e¨ |
1 | 2 | 3 | 4 | 5 | 6 | 87 | 8 | 9 | 10 | 11 | 12 |
06 | 2010-11 A_© eQ‡i PvUgvni Dc‡Rjvi ¸qvLovUZR ivgP›`ªcyi nvB¯‹zj fvqv Rv‡jk¦i iv¯—v (†PB‡bR 00- 2500 wgt) Dbœqb(c¨v‡KR bs- PAB-VR-71/10-11) | 92,95,725/= | 92,95,725/= | †gmvm© MvjvcKb÷ªvKkb ‡cÖvt †gvt †Mvjvc DwÏb Avn‡¤§`,†gvnbcyi,bv‡Uvi | 88,30,938/= | 09-11-10 | 12-08-2011 | 100% |
|
|
|
07
| 2011-12 A_© eQ‡i kirMÄ-Bw`jcyi evRvi fvqv RMbœv_cyi iv¯Ívq 350wgt,800wgt, 1200 wgt, 1950wgt,2100wgt I 2700wgt †PB‡b‡R QqwU BD†Wªb wbg©vY(c¨v‡KRbs-PAB-ST-UZR-16/10-11 | 370,806/= | 370,806/= | ‡gmvm© gv Kb÷ªvKkb †cÖvt-bvRg~j Avjx gvwj_v PK QvwZqvwb, cvebv| | 366,390/= | 28-12-11 | 03-02-12 | 100% |
|
|
|
08 | 2011-12 A_© eQ‡i mgvR-KiZKvw›` gmwR` moK Ges PvU‡gvni wWMÖx K‡jR moK Dbœqb (c¨v‡KR bs-PAB-VR-112/11-12) | 69,14,376/= | 69,14,376/= | †gmvm© Avjg GÛ eªv`vm© eªxKm, †ngv‡qZcyi cvebv| | 65,68,657/= | 11-01-12 | 17-07-12 | 25% |
|
|
|
09 | 2011-12 A_© eQ‡i Kvw›`cvov gmwR`-eo Mvidv moK Dbœqb (c¨v‡KR bs-PAB-VR-30/11-12) | 96,06,695/= | 96,06,695/= | †gmvm© weDwU K¨vwe‡bU ivavbMi, cvebv| | 91,26,360/= | 11-01-125 | 17-07-12 | 30% |
|
|
|
10 | 2011-12 A_© eQ‡i ivgbMi NvU BD‡RWAvi-nwicyi †Zwjcvov eUMvQ moK Dbœqb (c¨v‡KR bs-PAB-VR-110/11-12) | 57,03,860/= | 57,03,860/= | Rbve ‡gvt †mwjg †nv‡mb †Mvcvjcyi cvebv| | 54,18,667/= | 11-01-12 | 17-07-12 | 35% |
|
|
|
11 | 2011-12 A_© eQ‡i †evqvBjgvix †PŠiv¯Ív-ayjvDwo fvqv wgw¯¿cvov-SvuKov moK Dbœqb (c¨v‡KR bs-PAB-VR-113/11-12) | 53,59,312/= | 53,59,312/= | Rbve †gvt Avãyj Kv‡`i w`jvjcyi, cvebv| | 50,91,346/= | 11-01-12 | 17-07-12 | - |
|
|
|
12 | 2011-12 A_© eQ‡i PvU‡gvni AviGBPwW fv`ybMi evRvi-cvk¦©Wv½v BDwc fvqv myBMÖvg moK (†PB‡bR 1350-3850wgt) Dbœqb (c¨v‡KR bs-PAB-UNR-28/11-12) | 118,58,571/= | 118,58,571/= | ‡gmvm© Avn‡g` ibRy jvB‡eªix evRvi, AvUzqv cvebv| | 112,65,547/= | 12-01-12 | 17-07-12 | - |
|
|
|
13 | 2011-12 A_© eQ‡i fv`ªv AviGBPwW(g_yivcyi BDwc)-PoB‡Kvj nvU fvqv g_yivcyi ¯BP †MU moK (†PB‡bR 789-1289wgt) Dbœqb (c¨v‡KR bs-PAB-UNR-29/11-12) | 23,26,460/= | 23,26,460.00 | †gmvm© cÖMwZ G›UvicÖvB, evwjqvnvjU, cvebv|
| 22,10,137/= | 17-01-12 | 23-07-12 | - |
|
|
|
14 | 2011-12 A_© eQ‡i ‡eMg †iv‡Kqv mgvRx moK (†PB‡bR 500-1135wgt) Dbœqb (c¨v‡KR bs-PAB-VR-111/11-12) | 39,22,349.00 | 39,22,349.00 | †gmvm© L›`Kvi Kb÷ªvKkb, AvUNwiqv, cvebv| | 37,26,231/= | 17-01-12 | 23-07-12 | 70% |
|
|
|
wnmve i¶K Dc-mnKvix cÖ‡KŠkjx Dc‡Rjv cÖ‡KŠkjx
Dc‡Rjv cÖ‡KŠkjxi `ßi Dc‡Rjv cÖ‡KŠkjxi `ßi PvU‡gvni, cvebv|
PvU‡gvni, cvebv| PvU‡gvni, cvebv|
AMÖMwZ cÖwZ‡e`b/10
¯’vbxq miKvi cÖ‡KŠkj Awa`ßi
2009-2010 A_© eQ‡i cjx moK I KvjfvU© †gigZ Kg©m~Pxi AvIZvq M„nxZ cÖK‡íi gvwmK AMÖMwZi cÖwZ‡e`b
Dc‡Rjv t PvU‡gvni, †Rjvt cvebv| cÖwZ‡e`‡bi gvm/ZvwiLt- RybÕ2012
µwgK bs | cÖK‡íi bvg | ‡gvU eivÏ | cÖv°wjZ g~j¨ | wVKv`v‡ii bvg I wVKvbv | Pzw³g~j¨ (UvKv) | Kvh©v‡`‡ki ZvwiL | Kvh©v‡`k †gvZv‡eK KvR mgvwßi ZvwiL | Kv‡Ri AMÖMwZ | cÖvß A_© | ‡gvU e¨q | gš—e¨ |
1 | 2 | 3 | 4 | 5 | 6 | 87 | 8 | 9 | 10 | 11 | 12 |
01 | 2010-2011 A_© eQ‡i cjx moK I KvjfvU© †givgZ Kg©m~Pxi AvIZvq PvU‡gvni Dc‡Rjvaxb Periodic Maintenance of 4.00mX4.00m RCC Box Culvert Underpass on Mohela GCM-Sharatgonj GCM Via Parshawdanga hat road. | 20,32,682/= | 20,32,682/= | †gvt ivnvZ †PŠayix, AvUzqv †gv‡gbvev`, cvebv| | 19,31,047/= | 19-04-10 | 30-06-11 | 90% |
|
| Carried over |
02 | PvU‡gvni Dc‡Rjvaxb Periodic Mainte-nance of Chatmohar R & H at Janata Bank-Mirjapur GCM Via Noornagar road at Ch. 00-460m, 1700-2425m. (c¨v‡KR bs-Pab/GOBM/W-013)| | 18,78,785/= | 18,78,785/= | †gvt AvdRvj †nv‡mb, ebIqvix bMi evRiv, dwi`cyi, cvebv| | 17,85,050/= | 05-12-11 | 30-04-12 | 85% |
|
|
|
03 | 2011-2012 A_© eQ‡i cjx moK I KvjfvU© †givgZ Kg©m~Pxi AvIZvq PvU‡gvni Dc‡Rjvaxb Periodic Maintenance of Upazila H/Q(T & T more) Gopalpur GC Via Ramnagar GPS & Haripur UP road at Ch. 4300-6645m (c¨v‡KR bs-Pab/GOBM/ W-0014) | 27,69,090/= | 27,69,090/= | †gvt Avãyi iwng, Avï‡Zvlcyi, cvebv| | 26,31,500/= | 28-12-11 | 05-05-12 | 80% |
|
|
|
04 | PvU‡gvni Dc‡Rjvaxb Periodic Mainte-nance of Haripur UP-Khairash hat Via Katakhali hat road at Ch. 1700-5605m. (c¨v‡KR bs-Pab/GOBM/W-015)| |
42,48,000/= |
42,48,000/= |
BD,Gm,G K‡cv©‡ikb, evwjqv nvjU, cvebv| |
40,35,600/= |
13-12-11 |
30-04-12 |
100% |
|
|
|
wnmve i¶K DcmnKvix cÖ‡KŠkjx Dc‡Rjv cÖ‡KŠkjx
Dc‡Rjv cÖ‡KŠkjxi `ßi Dc‡Rjv cÖ‡KŠkjxi `ßi PvU‡gvni, cvebv|
PvU‡gvni, cvebv| PvU‡gvni, cvebv
AMÖMwZ cÖwZ‡e`b/11
¯’vbxq miKvi cÖ‡KŠkj Awa`ßi
cjx AeKvVv‡gv Dbœqb(Rb¸i“Z¡c~Y© MÖvgxY †hvMv‡hvM Ges nvU-evRvi D&bœqb I cybe©vmb)kxl©K cÖK‡íi
gvwmK AMÖMwZi cÖwZ‡e`b (A_© ermit............................)
Dc‡Rjvt PvU‡gvni, †Rjvt cvebv| cÖwZ‡e`‡bi gvm/ZvwiLt RybÕ2012
µwgK bs | cÖK‡íi bvg | ‡gvU eivÏ | cÖv°wjZ g~j¨ | wVKv`v‡ii bvg I wVKvbv | Pzw³g~j¨ (UvKv) | Kvh©v‡`‡ki ZvwiL | Kvh©v‡`k †gvZv‡eK KvR mgvwßi ZvwiL | Kv‡Ri AMÖMwZ | cÖvß A_© | ‡gvU e¨q | gš—e¨ |
1 | 2 | 3 | 4 | 5 | 6 | 87 | 8 | 9 | 10 | 11 | 12 |
01 |
PvU‡gvni Dc‡Rjvaxb avbKzwbqv evRvi Dbœqb (c¨v‡KR bs-Pab/PMP-2/W-53)| |
10,34,598/= |
10,34,598/= |
‡gmvm© mv‡R` Kb÷ªvKkb, ‡cÖvt- †K, Gg, mv‡R`yi ingvb, L›`Kvi gv‡K©U, Ck¦i`x|
|
785,101/72 |
09-02-11 |
16-06-11 |
100% |
|
|
|
02 | 2011-2011 A_© eQ‡i Ò cjx AeKvVv‡gv Dbœqb(Rb¸i“Z¡c~Y© MÖvgxY †hvMv‡hvM Ges nvU-evRvi Dbœqb I cybe©vmb)t 2q LÛÓ cÖK‡íi AvIZvq PvU‡gvni Dc‡Rjvaxb evgbMÖvg-`qvivgcyi iv¯Ív (†PB‡bR 00-1000wgt) Dbœqb (Package No.Pab/MPM-2/11-12/ W-003)- | 46,57,926/= | 46,57,926/= | †gvt Avãyj Kv‡`i, w`jvjcyi, cvebv|
| 44,25,029/= | 29-05-12 | 02-10-12 |
|
|
|
|
wnmve i¶K DcmnKvix cÖ‡KŠkjx Dc‡Rjv cÖ‡KŠkjx
Dc‡Rjv cÖ‡KŠkjxi `ßi Dc‡Rjv cÖ‡KŠkjxi `ßi PvU‡gvni, cvebv|
PvU‡gvni, cvebv| PvU‡gvni, cvebv|
AMÖMwZ cÖwZ‡e`b/13
¯’vbxq miKvi cÖ‡KŠkj Awa`ßi
Dc‡Rjv I BDwbqb mo‡K †cv‡U©ej w÷j eªxR wbg©vY cÖKí
Dc‡Rjvt PvU‡gvni, †Rjvt cvebv| cÖwZ‡e`‡bi gvm/ZvwiLt RybÕ2012
µwgK bs | cÖK‡íi bvg | ‡gvU eivÏ | cÖv°wjZ g~j¨ | wVKv`v‡ii bvg I wVKvbv | Pzw³g~j¨ (UvKv) | Kvh©v‡`‡ki ZvwiL | Kvh©v‡`k †gvZv‡eK KvR mgvwßi ZvwiL | Kv‡Ri AMÖMwZ | cÖvß A_© | ‡gvU e¨q | gš—e¨ |
1 | 2 | 3 | 4 | 5 | 6 | 87 | 8 | 9 | 10 | 11 | 12 |
01 |
2010-2011 A_© eQ‡i Dc‡Rjv I BDwbqb mo‡K †cv‡U©ej w÷j eªxR wbg©vY cÖK‡íi AvIZvq PvU‡gvni Dc‡Rjvaxb Construction of 96.00m PC Girder Bridge on Chhaikola GC-Naogoan GCM Via Sthal Ferryghat road over Korotoa river at Ch. 7400m.
|
280,58,075/= |
280,58,075/= |
†gmvm© fyjy miKvi GÛ †gvt Avwgbyj nK(†Rwf), AvjvBcyi, bv‡Uvi| |
301,37,244/= |
07-10-10 |
07-06-2011 |
45% |
|
| KvR Pj‡Q |
wnmve i¶K DcmnKvix cÖ‡KŠkjx Dc‡Rjv cÖ‡KŠkjx
Dc‡Rjv cÖ‡KŠkjxi `ßi Dc‡Rjv cÖ‡KŠkjxi `ßi PvU‡gvni, cvebv|
PvU‡gvni, cvebv| PvU‡gvni, cvebv|
AMÖMwZ cÖwZ‡e`b/13
MONTHLY PROGRESS REPORT FOR STRUCTURES ON UNION ROAD
AND VILLAGE ROAD TYPE-A(SUR) UNDER RDP-26(RTP)
FINANCIAL YEAR:2005-2006
DISTRICT: PABNA., UPAZILA: CHATMOHAR. Reporting Month: June’2012
Sl. No. | Upazila | Contract information | Name of the Work in/c. Chainage | Span (m) | Estimated Cost (Tk. in Lac) | Bid receiving date dd/mm/yy | Contract Signing date dd/mm/yy | Date of Work Order issued dd/mm/yy | Date of Commen-cement as per W/O d/mm/yy | Schedule Comple-tion date dd/mm/yy | Revised date of Com-pletion dd/mm/yy | Name of Contractor & Address | Cont-ract Amount (Tk. in Lac) | Re- vised Con- tract Amount (Tk.) | Pro- gress to date (%) | Pro- gress this month (%) | Fund sspent till date (Tk.) | Amount of SWP sent till date (Tk in Lac) | Remarks | ||
Package No. | Slice No. | RPA | G O B | ||||||||||||||||||
1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 | 9 | 10 | 11 | 12 | 13 | 14 | 15 | 16 | 17 | 18 | 19 | 20 | 21 | 22 |
01 | -do- | Pab-SUR- 992 | - | Handial U.P. office Samaj bazar road at Ch. 2+600Km.
| 20.00 | 3294042.87 | 22.11.06 | 12.03.07 | 12.03.07 | 18.03.07 | 14.03.08 | 15.08.08 | Md. Afzal Hossain, Faridpur, Pabna. | 3778979.6 | - | - | 100% |
|
| 3723462.00 | Final Bill |
02 |
| Pab-SUR- 88 | - | Handial U.P. office Samaj bazar road at Ch. 3+200Km.
| 20.00 | 3294042.87 | 27.12.06 | 12.03.07 | 12.03.07 | 12.03.07 | 14.03.08 |
| -do- | 3779172.6 | - | - | 100% |
|
| 1219500.00 | do |
03 |
| Pab-SUR-402 | - | Handial U.P. office Samaj bazar road at Ch. 3+000Km.
| 12.00 | 1495346.00 | 27.12.06 | 26.04.07 | 26.04.07 | 25.04.08 | 25.04.08 |
| Prime Construction Dhaka | 1715907.35 | - | - | 100% |
|
| 1601431.00 | do |
04 |
| Pab-SUR- 997 | - | Construction of 4.00x 4.00m Four Vent RCC Box Culvert on Purba Tiar tola R & H –Khatabari hat road at Ch. 1+500km | 16.00 | 1562808.00 | 27.12.06 | 17.04.07 | 17.04.07 | 16.04.07 | 16.04.08 |
| M/S. Baluchar ConstructionChatmohar, Pabna. | 1777602.06 | - | - | 100% |
|
| 1710395.00 | do |
05 |
| Pab-SUR- 998 | - | Construction of 4.00x 4.00m Four Vent RCC Box Culvert on Mohela GC-Diarpara R & H Via Boalia road at Ch. 3+000km | 16.00 | 1700841.00 | 27.12.06 | 23.03.08 | 01.04.08 | 31.03.09 | 31.03.09 |
| Md. Afzal Hossain, Faridpur, Pabna. | 1949449.00 | - | - | 100% |
|
| 1635573.00 | do |
06 | Cat-mohar | Pab-SUR- 763 | SUR-763.1 | Lohagara-Chaikola paschim para (Chaikola-Jhakra-Gangbera) road at Ch. 900m.
| 4.00 | 628190.00 | 27-12-06 | 20-01-09 | 20-01-09 | 20-01-08 | 20-01-09 | 20-01-08 | M/S. Akash Traders, Chatmohar, Pabna | 716949.81 |
| - | 100% |
|
| - | do |
07. | -do- | Pab-SUR- 763 | SUR-763.2 | Lohagara-Chaikola paschim para (Chaikola-Jhakra-Gangbera) road at Ch. 1500m.
| 4.00 | 632120.00 | 27-12-06 | 19-04-07 | 19-04-07 | 18-04-08 | 19-04-07 | 18-04-08 | M/S. Chaklader Construction Jessore | 721470.21 |
| - | 100% |
|
| 436415.00 | do |
08 | -d- | Pab-SUR- 350 | - | Lohagara-Chaikola paschim para (Chaikola-Jhakra-Gangbera) road at Ch. 3040m.
| 12.00 | 1495346.00 | 27-12-06 | 01-04-08 | 01-04-08 | 31-03-09 | 01-04-08 | 31-03-09 | A.B. Construction Chatmoahr, Pabna. | 1718509.12 |
| - | 100% |
|
| - | do |
Sub-Assistant Engineer, Upazila Engineer, Assistant Engineer, Assistant Engineer, Executive Engineer,
Chatmohar, Pabna. Chatmohar, Pabna. RTIP., LGED, Dist-Pabna. LGED., Dist.Pabna. LGED., Dist. Pabna.
Progress Report/15
MONTHLY PROGRESS REPORT FOR STRUCTURES ON UNION ROAD
AND VILLAGE ROAD TYPE-A(SUR) UNDER RDP-26(RTP)
FINANCIAL YEAR:2005-2006
DISTRICT: PABNA, UPAZILA: CHATMOHAR Reporting Month: June’2012
Sl. No. | Upazila | Contract information | Name of the Work in/c. Chainage | Span (m) | Estimated Cost (Tk. in Lac) | Bid receiving date dd/mm/yy | Contract Signing date dd/mm/yy | Date of Work Order issued dd/mm/yy | Date of Commen-cement as per W/O d/mm/yy | Schedule Comple-tion date dd/mm/yy | Revised date of Comple-tion d/mm/yy | Name of Contractor & Address | Cont-ract Amount (Tk. in Lac) | Re- vised Con- tract Amount (Tk.) | Pro- gress to date (%) | Pro- gress this month (%) | Fund sspent till date (Tk.) | Amount of SWP sent till date (Tk in Lac) | Remarks | ||
Package No. | Slice No. | RPA | GOB | ||||||||||||||||||
1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 | 9 | 10 | 11 | 12 | 13 | 14 | 15 | 16 | 17 | 18 | 19 | 20 | 21 | 22 |
09 | -do- | Pab-SUR-996 | - | Construction of 4.50x 5.00m Four Vent RCC Box Culvert on Gunaigacha R & H –Pailanpur road at Ch. 130km
| 18.00 | 2709322.00 | 27-12-06 | 17-04-07 | 17-04-07 | 16-04-08 | 17-04-07 | 16-04-08 | Dulal Karmaker, Chatmohar, Pabna | 3101278.75 |
| 100% |
|
|
| 1981380.00 | Final Bill |
10 | -do- | Pab-SUR- 126 | - | Improvement of Chhaikola hat(GCM) phase-1 under Chatmohar Upazila. | - | 2673746.00 |
|
| 29-11-07 | 28-11-08 |
|
| M/S. Tushar Enterprise, Radhanagar, Pabna. | 2541562.00 |
| 100% |
|
|
|
| do |
11 |
Chat- mohar |
Pab/F-8 | - |
a) Rehabilitation of Chatmohar T & T more-Horipur U.P. office Via Ramnagar & Dhulauri road(Ch. 00-3030m) b) Rehabilitation of ChaikolaGC-Kachikata GC road(00-2200m) c) Rehabilitation of Nimaichara U.P. office-Samaj bazar road(Ch.00-2100m, 3590-4000m & 4120-4800m) d) Rehabilitation of Chaikola U.P. Handial U.P. road(Ch..4040-5000m)
|
|
338.58 |
- |
- |
16.03.09 |
20.03.09 |
15-09.2010 |
|
National Construction Co. Ltd., House # 3, Road # 1/A, Section-4, Uttara, Dhaka |
331.27 |
- |
100%
100%
100% |
|
- |
- |
- |
|
12 | -do- | GCM-126.A
| - | Improvement of Chhaikola GCM.
| - | 35.40 | 20.05.09 | 11-03-10 | 16-03-10 | 02-11-10 | - | - | Md. Afzal Hossain, Faridpur, Pabna.
| - | - | 100% |
| - | - | - |
|
Sub-Assistant Engineer, Upazila Engineer, Assistant Engineer, Assistant Engineer, Executive Engineer,
Chatmohar, Pabna. Chatmohar, Pabna. RTIP., LGED, Dist-Pabna. LGED., Dist.Pabna. LGED., Dist. Pabna.
Progress Report/16
MONTHLY PROGRESS REPORT FOR STRUCTURES ON UNION ROAD
AND VILLAGE ROAD TYPE-A(SUR) UNDER RDP-26(RTP)
FINANCIAL YEAR:2008-2009
DISTRICT: PABNA., UPA ZILA: CHATMOHAR Reporting Month: June’2012
Sl. No. | Upazila | Contract information | Name of the Work in/c. Chainage | Span (m) | Estimated Cost (Tk. in Lac) | Bid receiving date dd/mm/yy | Contract Signing date dd/mm/yy | Date of Work Order issued dd/mm/yy | Date of Commen-cement as per W/O d/mm/yy | Schedule Comple-tion date dd/mm/yy | Revised date of Comple-tion d/ mm/yy | Name of Contractor & Address | Cont-ract Amount (Tk. in Lac) | Re- vised Con- tract Amount (Tk.) | Pro- gress to date (%) | Pro- gress this month (%) | Fund sspent till date (Tk.) | Amount of SWP sent till date (Tk in Lac) | Remar-ks | ||
Package No. | Slice No. | RPA | GOB | ||||||||||||||||||
1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 | 9 | 10 | 11 | 12 | 13 | 14 | 15 | 16 | 17 | 18 | 19 | 20 | 21 | 22 |
01 | Chat- mohar | PAB/SUR -1455 | SUR-1455.1 | b) Construction of 4.00x 3.00m Single Vent RCC Box Culvert on T & T more-Ramnagar road at Ch. 1700m | 4.00 | 806133.00 | 3.12.08 | 19.10-09 | 19.10-09 | 26.10.09 | 26.10. 2010 |
| Sarker Construction, Faridpur, Pabna | 8.90 |
| 100% | 100% |
|
|
| Final Bill |
SUR-1455.2 | a) Construction of 4.30x 3.00m Single Vent RCC Box Culvert on Samaj bazar-Khanmorich U.P. road at Ch. 1900m | 4.30 | 844026.00 | 3.12.08 | 4.11.09 | 4.11.09 | 11.11.09 | 11.11. 2010 |
| A.B. Cons-truction, Chat-mohar, Pabna | 9.51 |
| 100% | 100% |
|
|
| do | |||
SUR-1455.3. | c) Construction of 4.00x 3.00m two Vent RCC Box Culvert on Mohela GC-Diar para Via Boalia road at Ch. 3350m | 8.00 | 1007574.00 | 3.12.08 | 30.08.09 | 30.08.09 | 06.09.09 | 31.08. 2010 |
| Md. Afzal Hossain, Farid-pur, Pabna | 11.08 |
| 100% | 100% |
|
|
| do | |||
d02 | -do- | PAB/SUR -1456 | SUR-1456.1 | a) Construction of 4.00x 4.00m two Vent RCC Box Culvert on Haripur U.P. office Daya-rampur r oad over kata Jola at Ch. 1800m | 8.00 | 1434861.00 | 3.12.08 | 30.08.09 | 30.08.09 | 06.09.09 | 31.08. 2010 |
| -do- | 15.77 |
| 100% | 100% |
|
|
| do |
SUR-1456.2 | b) Construction of 4.00x 4.00m two Vent RCC Box Culvert on Haripur U.P. office Daya-rampur r oad over kata Jola at Ch. 2000m | 8.00 | 1434861.00 | 3.12.08 | 30.08.09 | 30.08.09 | 06.09.09 | 31.08. 2010 |
| -do- | 15.77 |
| 100% | 100% |
|
|
| do | |||
SUR-1456.3 | c) Construction of 4.00x4.00m two Vent RCC Box Culvert on Handial U.P. office-Samaj bazar road at Ch. 700m | 8.00 | 1434861.00 | 3.12.08 | 30.08.09 | 30.08.09 | 06.09.09 | 31.08. 2010 |
| -do- | 15.77 |
| 100% | 100% |
|
|
| do | |||
03 | -do- | PAB/SUR -1457 | SUR-1457.1 | a) Construction of 4.00x3.00m Three Vent RCC Box Culvert on Shibpur Bot Tola-Shahapur CARE road at Ch. 500m | 12.00 | 1355927.00 | 3.12.08 |
|
|
|
|
| A.B. Construc-tion, Chat-mohar, Pabna | 14.89 |
| 100% | 100% |
|
|
| do |
SUR-1457.2 | b) Construction of 4.00x 4.00m Three Vent RCC Box Culvert on Moheshpur R & H –Moheshpur road at Ch.150m | 12.00 | 1860345.00 | 3.12.08 | 20-07-09 | 20-07-09 | 26-07-2010 | 20-07-09 | 26-07-2010 | M/S. A.B. Construction Chatmohar Pabna. | 20.49 |
| 100% | 100% |
|
|
| do | |||
04 | -do- | PAB/SUR -1458 | - | Construction of 4.50x5.00m four Vent RCC Box Culvert on Mathurapur U.P. office-D.B.gram U.P. office road over Chor beel Jola at Ch. 3000m | 18.00 | 2522799.00 | 3.12.08 | 30.08.09 | 30.08.09 | 06.09.09 | 31.08. 2010 |
| M/S. Shahin Enterprise, Chatmohar, Pabna | 28.17 |
| 100% | 100% |
|
|
| do |
05 |
| PAB/SUR -1459 | - | Construction of 4.50x5..00m four Vent RCC Box Culvert on Haripur U.P. office-Dayarampur road over Kata Jola at Ch. 1700m | 18.00 | 2510034.00 | 3.12.08 | 02-0-09 | 02-0-09 | 09-09-09 | 09-.09-2010 |
| M/S. Katha Construction, Chatmohr, Pabna | 27.46 |
| 100% | 100% |
|
|
| do |
06 |
| PAB/SUR -1460 | - | Construction of 4.50x5.00m four Vent RCC Box Culvert on Samaj hat-Ashraf Jindani(R.) Madrasha road at Ch. 2000m | 18.00 | 2507549.00 | 3.12.08 | 27-08-2009 | 27-08-2009 | 05.09.09 | 05.09 2010 |
| M/S. Golap Construction, Mohonpur, Natore | 28.22 |
| 100% | 100% |
|
|
| do |
Sub-Assistant Engineer, Upazila Engineer, Assistant Engineer, Assistant Engineer, Executive Engineer,
Chatmohar, Pabna. Chatmohar, Pabna. RTIP., LGED, Dist-Pabna. LGED., Dist.Pabna. LGED., Dist. Pabna.
Progress Report/17
MONTHLY PROGRESS REPORT FOR STRUCTURES ON UNION ROAD
AND VILLAGE ROAD TYPE-A(SUR) UNDER RDP-26(RTP)
FINANCIAL YEAR:2005-2006
DISTRICT: PABNA, UPAZILA: CHATMOHAR Reporting Month: June’2012
Sl. No. | Upazila | Contract information | Name of the Work in/c. Chainage | Span (m)/ Length (m) | Estimated Cost (Tk. in Lac) | Bid receiving date dd/mm/yy | Contract Signing date dd/mm/yy | Date of Work Order issued dd/mm/yy | Date of Commen-cement as per W/O d/mm/yy | Schedule Comple-tion date dd/mm/yy | Revised date of Comple-tion d/mm/yy | Name of Contractor & Address | Cont-ract Amount (Tk. in Lac) | Re- vised Con- tract Amount (Tk.) | Pro- gress to date (%) | Pro- gress this month (%) | Fund sspent till date (Tk.) | Amount of SWP sent till date (Tk in Lac) | Remarks | ||
Package No. | Slice No. | RPA | GOB | ||||||||||||||||||
1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 | 9 | 10 | 11 | 12 | 13 | 14 | 15 | 16 | 17 | 18 | 19 | 20 | 21 | 22 |
01 | -do | Pab/UZR- 50A | UZR-50A-3 | Improvement of Mohela GCM-Saratgonj GCM Via Parshawdanga road (Ch. 00-5300m) FY-2008-09
| 5.300 |
|
| 21.08.08 | 21.08.08 | 04.05.10 | 04.05..10 | - | Foundations Engineers Ltd. house#18, Road #15, Sector-4, Uttara Model town, Dhaka | 545.71 | - | 93% |
|
|
|
|
|
02 | -do- | Pab/UZR- 50A | UZR-50A-1 | Improvement Chatmohar R & H Janata Bank- Ashtomonisha GCM Via Noorganar road (Ch. 00-3+337m) in/c. 100m bridge(FY-2008-09) | 3.300 | 390.09 |
|
|
|
|
| - | Sarker Golam Mohammed Co. Ltd. Salgaria, Pabna. | 366.85 | - | 100% |
|
|
|
|
|
03 | -do- | Pab/UZR- 50A | UZR-50A-4 | Improvement of Mohela GCM-Saratgonj GCM Via Parshawdanga road (Ch. 00-1500m) in/c.100m bridge(FY-2008-09) | 1.500 | 388.78 |
|
|
|
|
| - | -do- | 366.03 | - | 90% |
|
|
|
| Pzw³ evwZj Kiv n‡q‡vQ |
04 | -do- | Pab/RPM-132 | - | Maintenance & RS of Chatmohar- Jonail road(Ch.0+00-9+500Km.) |
| 59.277 |
| 21-11-10 | 21-11-10 | 05-12-10 | 30-06-11 | - | M/S. Azad and Brothers-Angira Electronics(JV), Gulshan, Dhaka | 64.558 | - | 100% |
|
|
|
|
|
05 | -do- |
| - | Improvement of Handial UP office- Noagoan GC via Hashupur-Boro Belay road(Ch.00-1000m) & Const of 5.00mX5.00m 3 vent RCC Box Culvert on Handial UP office-Samaj bazar Rd. at Ch.1300m | 1000m | 90.136 |
| 02-01-11 | 02-01-11 | 05-01-11 | 31-05-11 | - | M/S. Khandaker Shahin Ahamed, Prop. Khandaker Shahin Ahamed, Road No.1. Goal chamot, Faridpur. | 76.307 | - | 100% |
|
|
|
|
|
06 | -do- | Pab/RPM-111 | - | Maintenance of (a)Chatmohar UZ HQ(high shool more)-Mohela GC via Bri-Guakhara Rd. (Ch.00-8200 m) & (b) Mulgram RHD-Dashuria GC via D.B.gram UP office road Ch.00-6725m) |
8200m
6725m | 137.076 |
| 25-01-11 | 25-01-11 | 27-01-11 | 25-06-11 | - | M/S. Tushar Enterprise, Prop. Md. Fazlul Haque, Radhanagar, Pabna. | 146.542 | - | 100% |
|
|
|
|
|
07 | do | Pab/UR-79A | - | Improvement of Handial UP office- Samaj bazaar road at Ch.00-4914m (Remaining work) | 4914m | 189.992 |
| 12-08-10 | 21-09-10 | 28-09-10 | 30-06-11 |
| M/S. Dhrubo Construction, Library bazaar, Pabna | 189.992 |
| 100% |
|
|
|
|
|
Sub-Assistant Engineer, Upazila Engineer,
Chatmohar, Pabna. Chatmohar, Pabna.
Progress Report/18